BID Notice

Vari1001 Pvt. Ltd.

Details / requirements:

1 Introduction

1.1 About the project

Vari1001 Pvt Ltd. intends to construct a 20-litre jar drinking water production facility at Mirchaiya, Siraha District, Madesh Province, Nepal. The facility will treat raw water, wash returned jars, fill and store them, and load them onto delivery vehicles. The plot is 1,044.35 sq m (3.08 Kattha). The main building is a single-storey structure of about 173 sq m (17.5 m × 10.3 m overall), with a steel frame on RCC footings, 200 mm AAC block external walls and a CGI sheet roof. It contains the water treatment room, bottle washing room, filling and storage room, storage room, logistics office, male and female toilets, and a 2 m wide loading and unloading area. The site layout also provides for the overhead tank, septic tank and soak pit, DG set, parking, and the wastewater and neutralization area.

1.2 Purpose of this document

This document describes the work that bidders are expected to price and carry out. It must be read together with the working drawings, the Bill of Quantities (BOQ), the technical specifications and the conditions of contract issued in the tender package. The drawings are the Wonaw & Associates working drawing set. The BOQ covers civil, sanitary, electrical, HVAC, landscaping and interior work. If this document conflicts with the drawings or the BOQ, bidders must raise the conflict as a written clarification before the bid deadline.

2 Scope of Work

2.1 General

The contractor shall supply all labour, materials, equipment, supervision, transport, temporary works and services needed to construct and hand over the main building and the services and external works listed below complete, in accordance with the approved working drawings, the BOQ, the specifications and the relevant Nepal National Building Code and applicable standards.

2.2 Included in the contractor's scope

A. Preliminary and site work

  • Setting out against the grid and benchmarks, including the layout of anchor bolts for the steel columns, with approval by the client's engineer or authorized personnel from Vari1001 before excavation
  • Site clearing, levelling and demolition of any existing structures shown on the drawings or instructed by the client’s authorized key personnel.

B. Substructure and structure

  • Excavation, backfilling and compaction where specified.
  • Foundations, plinth beams and plinth filling.
  • Steel frame
  • Reinforcement (Fe 500), formwork and concrete (M20), with cube tests and rebar certificates submitted to the engineer
  • Roof structure.

C. Masonry and finishes

  • 200mm AAC block in the external walls with internal and external plaster & paint
  • Hollow cement board internal partition walls without plaster
  • Brick in foundation, soling, etc.
  • Floor finishes as shown with waterproofing where required.
  • Wall tiles in toilets and in wet process areas as specified, to the height shown on the sections.
  • Painting, internal and external with washable paint in areas as specified

D. Openings and metalwork

  • Supply and installation of aluminium doors, single-glazed aluminium windows and rolling shutters as per the drawings.
  • One metal gate, and MS grills for internal trenches (specify).

E. Building services

  • Concealed conduits and sleeves, boxes, and openings for electrical, plumbing and drainage, placed before casting
  • Electrical wiring, switches, sockets, lighting, distribution boards, power cables and trays, ATS panel, UPS main DB and Earthing and lightning protection.
  • Electrical equipment: 50 kVA diesel generator set, voltage stabilizer with bypass panel, ICT cabling and sockets, and the IP CCTV system.
  • HVAC: inverter split air conditioners with piping, drainage and electrical connections.
  • Plumbing, sanitary fixtures, floor drains, and internal drainage to the connection point.
  • Ventilation provisions such as openings and exhaust fan points.

F. External works within the BOQ

  • Tank pad and its foundations as shown on the plan.
  • Loading and unloading strip and vehicle yard paving, as itemized.
  • Surface drainage and connection to the discharge or treatment point
  • 1.2 KLD septic tank, eight 2' × 2' manholes and one soak pit, and the 1,000 L HDPE overhead tank with its fittings.

G. Interior work

  • Cabinets for the laboratory office with plywood body, laminate and granite top (2 sq m), including 1 ft of wall tile.

2.3 Excluded from the contractor's scope

The following will be supplied and installed by the client or separate contractors. The main contractor must coordinate with them but does not price them unless the BOQ says so.

  • Water treatment plant (filtration, RO, UV and related equipment)
  • Bottle washing, filling and capping machinery, conveyors and racks
  • Storage tanks and their pipework (the pad is included; the tanks are not)
  • Process piping and control panels
  • Loose furniture, curtains and plants, and office equipment

2.4 Coordination with other contractors

The main contractor shall:

  • Give other contractors access to the work, and agree a shared program
  • Leave openings, plinths, trenches and equipment bases to the dimensions given by the equipment suppliers
  • Hold coordination meetings [weekly] and keep minutes
  • Not close up any area before the design team or authorized personnel from Vari1001 has inspected concealed services

3 Programme and Milestones

  • Completion period: 5 months from the commencement date
  • Key milestones: [site handover], [foundation complete], [structure complete], [roof complete], [finishes complete], [handover]
  • Bidders shall submit a 5 month work schedule with their bid

4 Quality, Materials and Testing

  • All materials shall meet the specifications and be approved by the engineer before use, with samples for tiles, paint, doors, windows and sanitary ware.
  • Concrete and steel shall be tested as required: cube tests, slump tests and rebar tensile certificates.
  • Work found defective shall be rectified at the contractor's cost.
  • Daily site records, a progress photo log and monthly progress reports shall be kept

5 Health, Safety and Environment

  • The contractor shall provide a site safety plan, protective equipment for workers, and first aid
  • Workers shall be insured as required by the contract
  • Dust, noise, waste and water runoff shall be controlled, and construction waste disposed of lawfully

6 Permits and Approvals

  • The client will obtain the building permit and land approvals.  
  • The contractor will comply with the permit conditions and arrange the inspections required during construction

7 Handover Requirements

On completion the contractor shall provide:

  • Snag-free building, cleaned and ready for equipment installation
  • As-built drawings
  • Test reports, material certificates and warranty documents
  • Operation and maintenance information for installed items
  • Keys, and a signed handover certificate

8 Defects Liability

The contractor is responsible for correcting defects for [12] months from the handover date, as set out in the conditions of contract.

9 Bid Submission

9.1 Documents to submit

Each bid shall contain the following documents, in this order:

  • Cover letter and bid form, stating the total bid price, the validity period of the bid ([90] days) and acceptance of the conditions of contract
  • Company registration certificate, PAN/VAT registration and the latest tax clearance certificate
  • Priced BOQ: every item priced in the currency stated in the BOQ, with VAT shown separately, and no item left blank, altered or removed and the brands offered for items where the BOQ allows an equivalent
  • Valid construction business license and any other registration required to carry out the work.
  • Schedule showing the 5-month completion period and the milestones.
  • Key personnel: site engineer, supervisor and safety officer, with CVs and the experience of each
  • Experience: a list of similar works completed in the last [5] years (client, location, year), with completion certificates or client letters
  • List of subcontractors and suppliers for the steel, electrical, plumbing and HVAC work if any.
  • Any assumptions, exclusions or clarifications the bidder has made, listed in one separate document.

9.2 How to submit

Bids shall be submitted by email only. Hard copies will not be accepted.

Send one email to priya.shrestha@vari1001.com before [deadline: December 15. 2026, NPT]. Bids received after the deadline will not be considered.

The email subject line shall read: "Bid – Mirchaiya 20L Jar Water Plant – [Bidder name]".

Attach all documents as PDF files, signed and stamped by an authorized signatory, except the priced BOQ, which shall also be attached in its original Excel format. Name each file with the document number and bidder name, for example "03_Priced_BOQ_[Bidder name].pdf".

The client will confirm receipt by reply email within [2] working days. A bidder who has not received confirmation should contact the tender email address before the deadline.

Questions and clarification requests, including conflicts between this document, the drawings and the BOQ, shall be sent to the same email address by December 01, 2026. Answers will be sent to all bidders who have registered their interest.

9.3 Evaluation and award  

Bids will be checked for completeness first. Bids that lack the documents above may be rejected. The client may ask for originals, further details or a meeting before award, and is not bound to accept the lowest bid.

Vari1001 reserves the right to select and award the contract with more than one supplier based on its business requirements. The contract will be offered to the technically qualified bidder with a combined score of 70% technical and 30% price]. The client may negotiate minor points with the selected bidder, may reject all bids, and is not bound to give reasons for its decision.

Bids will be evaluated in two stages.

Stage 1: Compliance evaluation (10 points)

A bid that fails any of the following will not be evaluated further:

a. Received by email at the tender address before the deadline, in the format in Section 9.1

b. All documents in Section 9.2 are included, signed and stamped

c. Company registration, PAN/ VAT registration, tax clearance and construction business license are valid

d. The BOQ is fully priced, with no item left blank, altered or removed

e. Bid validity is at least [90] days.

Stage 2: Technical evaluation (90 points)

Bids that pass Stage 1 will be scored as follows.

Relevant experience: similar work in the last 5 years, their value and the completion certificates: [25] points

Key personnel: qualifications and experience of the site engineer, supervisor and safety officer: [25] points

Timeline: that meets the 5-month completion period: [15] points

Finance: Priced BoQ [25] points

Links:

Mirchaiya Plant Drawing Set

Mirchaiya BOQ for rate

Note: Bids priced far below the client's estimate or the other bids may be asked to justify their rates in writing. A bid that cannot justify its rates may be rejected.